ADU Rules in the City of San Mateo
The City of San Mateo processes compliant ADUs and JADUs ministerially with a building permit under Zoning Code Chapter 27.19. The city publishes flat ADU/JADU permit fees and posts pre-approved plan information. Unincorporated San Mateo County has a separate ordinance and coastal chapter.
This page covers the City of San Mateo, California only — not unincorporated San Mateo County and not other Peninsula cities. State law (Gov. Code §66310 et seq.) sets the floor; verify with the city before you design or build.
Yes, you can add an ADU or JADU in the City of San Mateo. Compliant projects are reviewed ministerially under Zoning Code Chapter 27.19 — typically a building permit and related permits, without a planning application or public notice when objective standards are met. The city publishes flat ADU/JADU permit fees and posts pre-approved plan resources; confirm current amounts before you budget.
Is your lot in the City of San Mateo?
Use the city’s Property Zone Look-Up Tool / Zoning Map linked from the ADU page. Also check FEMA flood mapping and Heritage Tree rules before you design. Building Division: (650) 522-7172 · building.info@cityofsanmateo.org. Planning: (650) 522-7212 · planning@cityofsanmateo.org.
City of San Mateo vs. San Mateo County
City parcels use City of San Mateo Building and Planning. Unincorporated areas use the County of San Mateo ADU pages (separate non-coastal Chapter 8.392 and coastal Chapter 8.396). Nearby cities differ again — see San José, San Francisco, and Oakland.
What the city’s ADU page says
When we checked the city’s ADU Information and Resources page, it said:
- Ministerial path. Compliant ADU/JADU applications need a building permit and related permits. A planning application with public notification is not required when objective ordinance standards are met.
- Definitions. An ADU is accessory to a primary residence with complete independent living facilities (attached, detached, or conversion). A JADU is created by converting existing floor area in a single-family dwelling, max 500 square feet, with separate living/sleeping/eating/cooking; sanitation may be separate or shared (shared bathroom requires interior access).
- Published permit fees (city page):
- Accessory Dwelling Unit (new) — $2,831.57 per unit (flat fee)
- Accessory Dwelling Unit (remodel) — $2,031.12 per unit (flat fee)
- Junior Accessory Dwelling Unit — $1,454.02 per unit (flat fee)
- The page also links a Comprehensive Fee Schedule — re-check amounts before you pay; schedules change.
- Handouts. Single-family and multifamily ADU handouts, plan submittal guide, pre-approved plans information, affordability survey, and development standards chart.
- AB 2533. Informational materials for certain unpermitted ADUs/JADUs.
- Other city links. County Assessor ADU tax FAQ, HCD Handbook, and third-party calculators appear on the resource list — older CalHFA links are not evidence of an open funding round. CalHFA’s December 28, 2023 update says the latest round was fully allocated, not that the entire program ended.
Submit through the city’s Online Permit Center (CSS portal).
Pre-approved and permit-ready plans
The city posts Pre-Approved ADU Plans Information and Submittal Guide materials and an ADU Plans Gallery on the ADU resources page, consistent with AB 1332 (Gov. Code §65852.27) duties. Use the city’s current guide for what is eligible and what site-specific work remains. See pre-approved ADU plans. We do not refer private designers.
ADU fees in San Mateo
Beyond the city’s flat ADU/JADU permit fees listed above, expect possible school fees, utility/sewer charges, C&D deposits, and other Public Works items depending on scope. The city’s residential plan-submittal guide (when available) notes school facilities fees for new residential units and additions over certain thresholds paid to the school district before permit issuance — confirm the current district threshold and amount; statewide Education Code / Gov. Code §66311.5(c)(3) uses a less than 500 square-foot assessable-space test for one school-fee purpose.
Impact fees (current law): Gov. Code §66311.5 (renumbered by SB 543, Stats. 2025, ch. 520, effective January 1, 2026) bars impact fees on ADUs with 750 square feet of interior livable space or less and JADUs with 500 square feet of interior livable space or less, with proportional fees above that. See ADU impact fees. Future, not current: From January 1, 2027, SB 1117 (Stats. 2026, ch. 809) changes proportional impact fees on ADUs over 750 square feet to cover only interior livable space above 750 for up to two ADUs on a lot; properties with more than two have a separate rule.
How long does an ADU permit take?
San Mateo directs applicants through its CSS Online Permit Center. Ask Building to identify the ADU completeness determination separately from portal intake and any related permits.
Under Gov. Code §66317, written completeness notice is due within 15 business days of receipt; missing it makes the application (including a resubmittal) deemed complete. For a completed application on a lot with an existing single-family or multifamily dwelling, the decision is due within 60 days, otherwise deemed approved. An applicant-requested delay tolls that period. With a concurrent new primary dwelling application, the agency may wait for the primary permit decision, but ADU review remains without discretion or a hearing. These are review clocks, not construction or move-in dates. For qualifying detached applications using a current-code-cycle preapproved or identical previously approved plan, §65852.27(b) provides a 30-day completed-application decision rule. See ADU permit timelines.
What does an ADU cost in San Mateo?
Aside from the published flat permit fees, we do not have city-specific construction cost data to cite. See our California ADU cost breakdown.
Frequently asked questions
Is the City of San Mateo different from San Mateo County for ADU permits?
Yes. A parcel inside the City of San Mateo follows city Chapter 27.19 and the city permit center. Unincorporated county parcels use the county’s separate ADU process, including its coastal rules where applicable. A San Mateo mailing address alone does not establish the permitting agency; use the city zoning lookup first.
Can I build a JADU in San Mateo?
A JADU is no more than 500 square feet of interior livable space, within the walls of a proposed or existing single-family residence; an attached garage counts, a detached accessory structure does not. It needs an efficiency kitchen and an entrance separate from the main entrance. Shared sanitation also requires interior entry to the main living area (Gov. Code §§66313(d), 66333(d)–(f)). Under Gov. Code §66333(b), owner-occupancy is required only if sanitation is shared: the owner may live in the main home or JADU. No owner-occupancy is required for separate sanitation, or when the owner is a governmental agency, land trust or housing organization. Confirm the required deed restriction with Planning.
Do I need a planning hearing?
Not for a compliant ministerial ADU/JADU. The city separately describes a discretionary alternative path for proposals that do not meet objective standards — ask Planning before you choose that route.
Is SB 9 the same as an ADU?
No. See SB 9 vs ADU.
Can I sell my San Mateo ADU separately?
Usually not unless the city has opted into AB 1033. We did not find an official city opt-in statement on the ADU page we checked — ask Planning. See selling an ADU separately.
Is there a state grant for ADUs?
CalHFA’s ADU Grant page states in its December 28, 2023 update: “The latest round of ADU funding has been fully allocated.” That describes the funding round, not a declaration that the entire program ended. Do not assume a new round is open; check CalHFA’s current notices before relying on assistance.
Official links
State-law and key local-source recheck: November 6, 2026. Posted amounts and programs can change; resolve the specific conflicts noted above before relying on them.
- City of San Mateo — ADU Information and Resources
- Online Permit Center
- Building (650) 522-7172 · Planning (650) 522-7212
- County of San Mateo — Accessory Dwelling Units (unincorporated)
- HCD ADU Handbook
- California HCD ADU page
For statewide rules, see our California ADU guide and California ADU laws for 2027.
Browse the California housing education hub for related guides.
HomeBuyers Alliance is a nonprofit. We don’t sell ADUs, refer contractors, or take payment from builders. This page is general information, not legal advice. Rules change, so confirm everything with the City of San Mateo before you design, buy, or build.
Primary sources
- City of San Mateo — Accessory Dwelling Unit Information and Resources — Zoning Code Chapter 27.19
- City of San Mateo — Online Permit Center
- County of San Mateo — Accessory Dwelling Units — Unincorporated only
- HCD Accessory Dwelling Unit Handbook — Gov. Code §66310 et seq.; §66311.5; §66317
- California HCD — Accessory Dwelling Units
- Gov. Code §66311.5 — ADU fees — Current text checked November 6, 2026
- Gov. Code §66317 — ADU review clocks — Current text checked November 6, 2026
- Gov. Code §66313 — ADU and JADU definitions — Current text checked November 6, 2026
- Gov. Code §66333 — JADU requirements — Current text checked November 6, 2026