ADU Rules in the City of Huntington Beach
Huntington Beach provides ministerial review for ADUs and JADUs under current state ADU law. The city offers a city pre-approved one-story detached 490-square-foot plan under AB 1332 with no modifications allowed. Coastal Zone projects may need a Coastal Development Permit.
This page covers the City of Huntington Beach, California only. If your parcel is in unincorporated Orange County or another city, different local rules apply. State law (Gov. Code §66310 et seq.) sets the floor; verify with the city before you design or build.
Yes, Huntington Beach accepts ADU and JADU applications with ministerial review under current state ADU law. The city posts a city pre-approved one-story detached 490-square-foot ADU plan under AB 1332 (no modifications allowed). Coastal Zone projects may also need a Coastal Development Permit. State law exempts ADUs of 750 square feet of interior livable space or less from impact fees, not every permit, school or utility charge. Ask the Permit Center for an itemized estimate.
Is your lot in the City of Huntington Beach?
Confirm your address is inside city limits before you rely on this page. Apply and track permits through the city’s online Accela portal linked from the Permit Center. Questions: Planning (714) 536-5511; Permit Center (714) 536-5271 · PermitCenter@surfcity-hb.org.
City of Huntington Beach vs. Orange County
City parcels use Huntington Beach Planning and the Permit Center. Unincorporated Orange County uses OC Development Services, which posts its own pre-approved plan catalog (the county notes some plan sets still reflect 2022 codes while 2025 updates are in progress). Nearby Orange County cities have separate guides — see Anaheim, Irvine, Santa Ana, and Laguna Niguel.
What the city’s ADU page says
When we checked the city’s ADU page and related Permit Center pages, they said:
- Applications continue. Per City Council direction (March 7, 2023), staff continues accepting ADU applications.
- Local ordinance superseded. Former HBZSO §230.10 ADU rules are no longer in effect after statewide ADU/JADU laws effective January 1, 2020. The city provides ministerial review for ADUs and JADUs.
- Coastal Zone. Development in the Coastal Zone may require Coastal Development Permits. That is parcel-specific — not every Huntington Beach lot is coastal. See our ADU coastal zone guide.
- Standards handout. The city points applicants to its ADU Handout for development standards and to the HCD ADU Handbook for statewide context.
- Building codes. The Permit Center states the 2025 California Building Standards Code took effect January 1, 2026. Incomplete applications after March 31, 2026 may be voided and need resubmittal under 2025 codes.
- Issuance extras for new ADUs. The Permit Issuance Process page says new ADUs/JADUs need a separate Planning application for address assignment; its page broadly mentions developmental impact fees for new homes, ADUs and additions over 500 sq ft, but that wording does not override the current ADU exemption through 750 square feet of interior livable space (see fees below); solar PV may be required under Title 24 on a separate permit before framing inspection.
Pre-approved and permit-ready plans
Pursuant to AB 1332 (Gov. Code §65852.27), Huntington Beach offers an HB Pre-Approved ADU Plan: currently a 1-story, detached 490-square-foot unit. The city says using it can save design time and cost, and that modifications or deviations are not allowed. Brochure and plan-set links are on the city’s ADU and Permit Center pages. Site-specific permits are still required. See pre-approved ADU plans.
ADU fees in Huntington Beach
The Permit Issuance Process page broadly says developmental impact fees apply to new homes, ADUs and additions over 500 sq ft. For an ADU, that general instruction must be reconciled with current §66311.5(c)(1): no impact fee at 750 square feet of interior livable space or less. If quoted an impact fee for a 501–750-square-foot ADU, request the fee category and legal basis in writing; do not treat the city’s older general note as a new ADU threshold. Building-permit fees, school fees and utility connection/capacity charges are different categories, each with its own rules. We do not quote a total project fee.
Under current state law (Gov. Code §66311.5, renumbered by SB 543, Stats. 2025, ch. 520, effective January 1, 2026), impact fees may not be imposed on an ADU with 750 square feet of interior livable space or less (or a JADU with 500 square feet of interior livable space or less); larger ADUs must be charged proportionately. Connection/capacity charges are separate but have their own limits and conversion-unit exemptions in §66311.5(b), (d) and (e). Details: ADU impact fees. Future, not current: From January 1, 2027, SB 1117 (Stats. 2026, ch. 809) changes proportional impact fees on ADUs over 750 square feet to cover only interior livable space above 750 for up to two ADUs on a lot; properties with more than two have a separate rule.
How long does an ADU permit take?
Huntington Beach publishes a ministerial path, not a separate ADU-only calendar guarantee on the pages checked. Ask the Permit Center to distinguish building review from any required coastal permit.
Under Gov. Code §66317, written completeness notice is due within 15 business days of receipt; missing it makes the application (including a resubmittal) deemed complete. For a completed application on a lot with an existing single-family or multifamily dwelling, the decision is due within 60 days, otherwise deemed approved. An applicant-requested delay tolls that period. With a concurrent new primary dwelling application, the agency may wait for the primary permit decision, but ADU review remains without discretion or a hearing. These are review clocks, not construction or move-in dates. For qualifying detached applications using a current-code-cycle preapproved or identical previously approved plan, §65852.27(b) provides a 30-day completed-application decision rule. See ADU permit timelines.
What does an ADU cost in Huntington Beach?
No city-specific construction cost figure we can cite. See our California ADU cost breakdown.
Frequently asked questions
Can Huntington Beach charge impact fees on a 600-square-foot ADU?
Not under current §66311.5(c)(1), if 600 square feet is its interior livable space. The exemption includes ADUs of 750 square feet or less. It is not an exemption from all building, school or utility charges. Ask the Permit Center to itemize each fee and reconcile any impact-fee quote with the statute.
Can I build a JADU in Huntington Beach?
A JADU is no more than 500 square feet of interior livable space, within the walls of a proposed or existing single-family residence; an attached garage counts, a detached accessory structure does not. It needs an efficiency kitchen and an entrance separate from the main entrance. Shared sanitation also requires interior entry to the main living area (Gov. Code §§66313(d), 66333(d)–(f)). Under Gov. Code §66333(b), owner-occupancy is required only if sanitation is shared: the owner may live in the main home or JADU. No owner-occupancy is required for separate sanitation, or when the owner is a governmental agency, land trust or housing organization. Confirm the required deed restriction with Planning.
Do I need a Coastal Development Permit?
Only if your project is in the Coastal Zone and the city/Coastal Commission require one. Ask Planning to map your parcel. See ADU coastal zone.
Is SB 9 the same as an ADU?
No. See SB 9 vs ADU.
Can I sell my Huntington Beach ADU separately?
Usually not unless the city has adopted an AB 1033 opt-in. We did not find an official opt-in statement on the ADU page we checked — ask Planning. See selling an ADU separately.
Is there a state grant for ADUs?
CalHFA’s ADU Grant page states in its December 28, 2023 update: “The latest round of ADU funding has been fully allocated.” That describes the funding round, not a declaration that the entire program ended. Do not assume a new round is open; check CalHFA’s current notices before relying on assistance.
Official links
State-law and key local-source recheck: November 6, 2026. Posted amounts and programs can change; resolve the specific conflicts noted above before relying on them.
- City of Huntington Beach — Accessory Dwelling Units
- Permit Center
- Permit Issuance Process
- Planning (714) 536-5511 · Permit Center (714) 536-5271 · PermitCenter@surfcity-hb.org
- OC Development Services — Pre-Approved ADU Plans (unincorporated)
- HCD ADU Handbook
- California HCD ADU page
For statewide rules, see our California ADU guide and California ADU laws for 2027.
Browse the California housing education hub for related guides.
HomeBuyers Alliance is a nonprofit. We don’t sell ADUs, refer contractors, or take payment from builders. This page is general information, not legal advice. Rules change, so confirm everything with the City of Huntington Beach before you design, buy, or build.
Primary sources
- City of Huntington Beach — Accessory Dwelling Units — AB 1332 / Gov. Code §65852.27
- City of Huntington Beach — Permit Center — 2025 California Building Standards Code effective Jan 1, 2026
- City of Huntington Beach — Permit Issuance Process
- OC Development Services — Pre-Approved ADU Plans — Unincorporated Orange County
- HCD Accessory Dwelling Unit Handbook — Gov. Code §66310 et seq.; §66311.5; §66317
- California HCD — Accessory Dwelling Units
- Gov. Code §66311.5 — ADU fees — Current text checked November 6, 2026
- Gov. Code §66317 — ADU review clocks — Current text checked November 6, 2026
- Gov. Code §66313 — ADU and JADU definitions — Current text checked November 6, 2026
- Gov. Code §66333 — JADU requirements — Current text checked November 6, 2026