How Do I Get an Unpermitted ADU Permitted in California?

California limits when a city can deny a permit for an unpermitted ADU built before January 1, 2020, and lets some owners request a five-year delay in enforcing building-code violations that aren't health and safety issues. New delay requests must be approved before January 1, 2030. Legalizing still means applying, inspections, and likely corrections.

The short answer

California limits when a city can deny a permit for an unpermitted ADU built before January 1, 2020. Owners of some ADUs can also request a five-year delay in enforcement of building-code violations that aren’t health and safety issues. New delay requests must be approved before 2030. Legalizing still means applying, inspections, and likely repairs.

California only

This page covers California state ADU law (Gov. Code §66310 et seq.) and related Health and Safety Code rules. Other states differ. How cities run legalization varies a lot. Verify with your city or county building department.

About HomeBuyers Alliance

HomeBuyers Alliance is a 501(c)(3) nonprofit. We make no contractor referrals and don’t sell plans. This guide is education only. It isn’t legal advice, and there’s no guaranteed “amnesty.”

Many California backyard units and garage conversions were built without permits. If you own one, or you’re buying a home with one, state law gives you more options than it used to. It doesn’t make the unit legal on its own, though. You still have to apply, let an inspector see it, and fix what needs fixing. For the statewide basics, see our California ADU guide.

Is my unit unpermitted, or just undocumented?

Start by finding out what’s on record. Sometimes a unit was permitted years ago, but the paperwork is hard to find.

  • Ask your building department for the permit history of your address. Many cities offer an online records search or a records request form.
  • Check the county assessor’s record for the property. It may list a second unit or extra square footage.
  • Look at sale documents from when you bought the home, like disclosures and inspection reports.

If you find a final permit for the unit, it may already be legal. If you find permits that were opened but never finished, or no permits at all, the rest of this guide applies.

Two state protections, explained

California has two separate rules for unpermitted ADUs. They’re often mixed up.

1. Limits on denying a permit (pre-2020 units)

Under Gov. Code §66311.7, a local agency shall not deny a permit for an unpermitted ADU built before January 1, 2020 just because it violates building standards, doesn’t meet state ADU law, or doesn’t meet the local ADU ordinance. HCD’s 2026 Handbook says AB 2533 (2024) moved this date up from 2018 to 2020, starting January 1, 2025.

The Handbook also says that under AB 2533:

  • An inspector may check the unit for health and safety and recommend what to fix.
  • The agency can’t penalize you just for having had the unpermitted unit, and must approve the permits needed to correct health and safety problems.
  • The agency must post information for the public, including a checklist of conditions that make a building “substandard.”
  • Before applying, you may get a confidential third-party code inspection from a licensed contractor to see what the unit may need.
  • Impact fees and utility connection or capacity charges are limited, except in specified circumstances.

2. The five-year enforcement delay

This is a different tool. Under Gov. Code §66331 and Health and Safety Code §17980.12, if a city issues you a notice to correct a building-code violation on a qualifying ADU, you can apply to delay enforcement for five years. A unit qualifies if it was:

  • Built before January 1, 2020, or
  • Built on or after that date in a place whose ADU ordinance wasn’t compliant with state law at the time, but is now.

The agency must grant the delay if correcting the violation isn’t necessary to protect health and safety. It must consult the agency that enforces State Fire Marshal rules when deciding.

Key dates, from the statute:

  • New delay requests: the agency can’t approve any on or after January 1, 2030.
  • Delays already approved before 2030 last their full five-year term.
  • The section itself is repealed on January 1, 2035.

So the delay program winds down in 2035, but new approvals stop in 2030. If you think you’ll need it, don’t assume you have until 2035 to ask.

The health and safety exception

Both protections have the same big limit. A city may still deny a permit, or refuse a delay, if fixing the problem is necessary to protect health and safety, or if the building is “substandard” under Health and Safety Code §17920.3.

Common examples of health and safety issues include unsafe wiring, no safe exit, gas or venting problems, structural hazards, and sewage problems. Your building department decides what counts. HCD notes these calls are within local discretion. If you disagree with a correction or denial, the Handbook points to the local appeals process.

Step-by-step legalization path

California only. Rules vary — verify each step with your city or county.

  1. Pull your records (permit history, assessor record, sale documents).
  2. Read your city’s legalization information. Look for its substandard-conditions checklist and any special program for existing units.
  3. Consider a confidential third-party inspection from a licensed contractor before you apply, so you know what you’re facing. Our contractor quote checklist can help you compare bids for the work.
  4. Ask the city (a pre-application meeting if offered): Which fees apply? Do I need plans drawn of the unit as built? Will they need to open walls?
  5. Apply for the permit to legalize the ADU. You’ll likely need as-built plans.
  6. Schedule inspections. Expect corrections. Some may require opening walls or ceilings.
  7. Make the required repairs under permit, with licensed trades where required.
  8. Get final sign-off and a certificate of occupancy before anyone lives there under the new permit.

For how state review timelines work, see our ADU permit timeline guide. Want to map what your existing unit needs? The free ADU planner can help organize it.

Honest risks

Legalizing usually pays off in peace of mind, but it isn’t risk-free.

  • Inspection findings. Once you apply, the city sees the unit. If it finds health and safety problems, you may have to fix them, and possibly stop using the unit until you do.
  • Costs. Fees, plans, and repairs vary widely by city and by the unit’s condition. We don’t have a reliable statewide range, so get local quotes.
  • Tenants. If someone lives in the unit, legalization can affect your rental arrangement. Ask a local tenant or legal resource before you start.
  • Property taxes. Newly permitted construction may be assessed. See our ADU property taxes guide.
  • Not applying has risks too. Unpermitted units can create problems with insurance, financing, sale, and safety.

We’d never suggest hiding a unit. If you’re unsure, a local attorney or your building department can explain your options.

Buying or selling a home with an unpermitted unit

If you’re buying, ask the seller for permit records and read disclosures closely. Lenders and appraisers may treat an unpermitted unit differently. See our buying a home with an ADU guide for questions to ask.

Frequently asked questions

Can my city deny a permit for my unpermitted ADU?

For units built before January 1, 2020, only in limited cases. A city can’t deny the permit just for code or ordinance problems, but it can if fixing a violation is needed for health and safety, or if the building is substandard (Gov. Code §66311.7).

Is there an amnesty for unpermitted ADUs in California?

Not a blanket one. State law limits permit denials and allows a five-year enforcement delay in some cases. You still apply, get inspected, and make required fixes.

How long can enforcement be delayed?

Five years, if approved. New approvals stop on January 1, 2030. Delays approved before then last their full term (Health and Safety Code §17980.12).

My unit was built after 2020. Am I out of luck?

Not always. The enforcement delay also covers units built after 2020 where the local ADU ordinance wasn’t compliant at the time but is now. Ask your building department.

Will legalizing my ADU raise my property taxes?

It can. New permitted construction may be assessed. See our ADU property taxes guide and ask your county assessor.

Sources

Every unit’s story is different. Your city’s building department is the right place to start.

Primary sources