How to Compare ADU Contractor Quotes in California
ADU bids often differ because they cover different work. Line quotes up item by item, check what each one leaves out, confirm the contractor's license with California's Contractors State License Board (CSLB), and keep the down payment within CSLB's rule: no more than 10% of the contract price or $1,000, whichever is less.
To compare ADU quotes in California, line them up item by item: design, permits and fees, site work, utilities, the building itself, and finishes. Check what each bid excludes, confirm the contractor’s license with the state board (CSLB), and watch the down-payment amount. Big price gaps usually mean different scopes.
The checklist below works almost anywhere. The license and deposit rules are California-only. They come from the Contractors State License Board (CSLB). Other states have different rules. Local permit steps and fees also vary, so check with your city or county.
HomeBuyers Alliance is a nonprofit. We don’t sell ADUs, and HBA makes no contractor referrals. This page is general information, not legal advice.
Why ADU bids differ so much
Homeowners online describe getting bids that range from about $180,000 to $400,000 for what looked like the same ADU (Reddit, Reddit). Those are anecdotes, not survey data. But the pattern is common, and the reasons are usually simple:
- Different scope. One bid includes design, permits, and utility work. Another starts at the foundation.
- Exclusions. “Permits, fees, and utilities by owner” can move a lot of cost off one bid and onto you.
- Allowances. A low finish allowance (for cabinets, flooring, fixtures) makes a bid look cheaper until you pick real products.
- Site conditions. Slopes, trenching distance, and panel upgrades change the price. Some bidders price them in. Others add them later as change orders.
So a low number isn’t always a better deal. First make the bids cover the same work. For typical cost ranges, see our California ADU cost breakdown.
Line-item checklist
Ask each bidder to price every row, or to write “not included.” Print this table and fill in one column per bid.
| Line item | What to look for | Bid A | Bid B | Bid C |
|---|---|---|---|---|
| Design and engineering | Plans, structural, energy (Title 24) calcs, revisions | |||
| Permits and city fees | Who pulls permits; who pays plan check and permit fees | |||
| Impact and school fees | Included, estimated, or owner-paid (impact fees) | |||
| Utility hookups | Water, sewer, electric, gas; panel upgrade; trenching (utility costs) | |||
| Site prep and grading | Demolition, tree removal, soil tests, grading, drainage | |||
| Foundation | Type and any soil-based changes | |||
| Structure | Framing, roof, windows, doors, insulation | |||
| Mechanical, electrical, plumbing | HVAC, water heater, wiring, fixtures | |||
| Finishes and allowances | Dollar amount for each allowance, and what it buys | |||
| Cleanup and final | Debris haul-off, final inspection, certificate of occupancy | |||
| Contingency | Is there one? Who controls it? |
If one row is blank on one bid, that bid isn’t comparable yet. Ask before you compare totals.
Red flags
- Vague allowances, or none at all
- “Permits extra” with no estimate
- Pressure to sign today or “lock in” a price
- Cash-only payment
- No written contract, or a contract that doesn’t match the bid
- A license number that doesn’t match the name on the bid
- A big payment up front (see the next section)
The license and down-payment rules below come from California’s Contractors State License Board. Other states differ.
California license and deposit rules
Check the license. Use CSLB’s free license lookup. Confirm the license is active, the name matches, and the classification fits the work. The lookup also shows bonds and any posted complaints or actions.
Watch the down payment. CSLB says the down payment on a home improvement job should never exceed 10% of the contract price or $1,000, whichever is less (CSLB). On a $250,000 ADU, that’s $1,000, not $25,000.
CSLB notes one rare exception. A contractor with a Blanket Performance and Payment Bond on file with CSLB may ask for more up front. CSLB says only about two dozen companies are approved for this bond. You can see it in the license lookup. If a bidder asks for more than the rule allows, ask them to show you that bond on CSLB’s site.
Get it in writing. CSLB advises a written contract with the total price, the payment schedule, and any cancellation terms. Read CSLB’s contract guidance before you sign. For anything you’re unsure about, ask CSLB or a lawyer.
Payment schedules tied to finished work
After the down payment, a fair schedule pays for work that’s done, not work that’s promised. Look for payments tied to clear milestones, such as:
- Foundation poured and inspected
- Framing complete and inspected
- Rough plumbing, electrical, and mechanical inspected
- Drywall and finishes complete
- Final inspection passed
Avoid schedules where payments get ahead of the work. Keep a copy of each inspection sign-off with each payment.
Questions to ask every bidder
- What exactly is included, and what is excluded?
- Who handles permits, and are permit and city fees in the price?
- Are impact, school, and utility connection fees included or estimated?
- What does each allowance cover, in dollars?
- What happens if the city asks for plan changes?
- How do you price change orders?
- What’s your license number, and does it match this bid?
- Who will be on site, and do you use subcontractors?
- What’s the payment schedule, and what milestone triggers each payment?
- What warranty do you offer, and is it in writing?
Timelines depend on your city’s review and inspections, so no bidder can promise a permit date. For what drives timing, see our permit timeline guide.
Why HBA doesn’t recommend contractors
We’re a nonprofit, and we stay neutral. HBA doesn’t name, rank, or refer contractors or design firms, and we don’t take referral fees. This checklist is meant to help you compare any bids you get, on your own terms.
If you’re also looking at funding, our ADU grants page explains what’s real. The CalHFA ADU Grant was a past program; HCD says its funds are used up.
Frequently asked questions
How much can a contractor ask for as a down payment in California?
CSLB says the down payment on a home improvement job should never be more than 10% of the contract price or $1,000, whichever is less. A rare exception applies to contractors with a Blanket Performance and Payment Bond on file with CSLB.
Do ADU quotes usually include permits?
Some do and some don’t. Ask each bidder whether permit fees, plan check, impact fees, and utility connection fees are included, estimated, or paid by you.
Why are my ADU bids so far apart?
Usually because they cover different work. Exclusions, allowances, and site work are the most common causes. Compare line by line before you compare totals.
How do I check a California contractor’s license?
Use CSLB’s free online license lookup. Confirm the license is active, the name matches the bid, and the classification fits the job.
Can HBA recommend an ADU contractor?
No. HBA makes no contractor referrals. We provide neutral checklists like this one.
For the statewide basics, see our California ADU guide and first-steps checklist. Before you collect bids, the free ADU planner can help you list what your project might include.
Primary sources
- CSLB — Contracts and Binding Agreements (down payment rule) — Accessed Nov 2, 2026 PT
- CSLB — Check a License — Accessed Nov 2, 2026 PT
- CSLB — Hire a Contractor — Accessed Nov 2, 2026 PT
- HCD Accessory Dwelling Unit Handbook (March 2026) — Accessed Nov 2, 2026 PT; Gov. Code §66310 et seq.
- California HCD — Accessory Dwelling Units
- Reddit r/LosAngelesRealEstate — homeowner thread on ADU builders (anecdotal)
- Reddit r/SouthBayLA — homeowner thread on ADU companies (anecdotal)