ADU Rules in the City of Modesto
Modesto reviews ADU and JADU building permits through Building Safety and Planning, with an optional ADU Express same-day review path for qualifying ministerial projects. Free partner plan sets from a Stanislaus County multi-city program are available for detached new construction, and every project still needs a city permit.
This page covers the City of Modesto, California only. If your parcel is in unincorporated Stanislaus County or another city, different local rules apply. State law (Gov. Code §66310 et seq.) sets the floor; verify with the city before you design or build.
Yes, you can add an ADU or junior ADU (JADU) in Modesto. Apply for an ADU building permit through the city’s eTRAKiT system after checking zoning with Planning. Modesto also offers an ADU Express appointment path that can approve qualifying ministerial plans the same day — participation does not guarantee approval. Free detached plan sets from a Stanislaus County multi-city partnership are available; you still need a city permit.
Is your lot in the City of Modesto?
Confirm your address is inside Modesto city limits before you follow this page. Bring a site sketch to the Planning and Building counter (City Hall, 1010 Tenth Street, Suite 3100) or email Planning at planning@modestogov.com / call 209-577-5267. The city points applicants to Modesto Municipal Code §10-4.115 and Table 4.1-3 for zoning standards. If your ADU would be a second story on a garage and neighboring homes are all single-story, the city says you may need an administrative review.
City of Modesto vs. Stanislaus County
Inside city limits, Modesto Building Safety and Planning review your ADU. Unincorporated Stanislaus County uses county Planning & Community Development and the county’s Accela portal. The county’s ADU page also hosts the free partner plan sets used inside Modesto. For regional comparison, Stockton, Fresno and Sacramento each have their own rules — see our Stockton, Fresno, and Sacramento pages.
What the city’s ADU page says
When we checked Modesto’s ADU page, it walked through an eight-step path:
- Create a site plan showing the existing house and all structures.
- Get Planning advice on setbacks and zoning before building-permit submittal.
- Apply online in eTRAKiT: create an account → Permitting → Apply for a permit → select ADU.
- Hire licensed professionals for design and construction (city advice, not a referral).
- Pay fees online or in person; the issued permit posts to eTRAKiT.
- Construct and pass inspections.
The page also describes ADU Express: a one-hour appointment with city staff for coordinated plan review. Qualifying ministerial ADU/JADU projects with complete, professionally prepared plans may receive same-day approval. The city states that participation is not a promise of approval and that plans must still meet zoning, building, and safety requirements. Schedule by calling 209-577-5232, ext. 0 (9 a.m.–3 p.m.) or emailing Permits@modestogov.com.
New address: After you have an ADU building permit, apply through Planning for a separate address. The city lists the current new-address fee as $197.
Modesto’s page still links CalHFA ADU Grant materials and a private credit-union loan partner. CalHFA’s ADU Grant page states in its December 28, 2023 update: “The latest round of ADU funding has been fully allocated.” That describes the funding round, not a declaration that the entire program ended. Do not assume a new round is open; check CalHFA’s current notices before relying on assistance. We do not promote private lenders here.
Pre-approved and permit-ready plans
Stanislaus County, in partnership with Modesto and other valley cities, posts free detached new-construction ADU plan sets for use in those partner jurisdictions. When we checked the county ADU page, it listed three plan sets — 405, 744, and 1,192 square feet — noted as compatible with the 2025 California Building Code, with floor plans and elevations available free (complete construction documents still come through the building-permit process). The city page still describes seven (7) plans, whereas the county page currently lists three 2025-code plan sets and says the 1,192-square-foot complete set will be available soon. Those posted counts and availability statements do not fully agree; ask Modesto which current complete set it accepts for your site before selecting a plan. The city also says it is collecting examples of pre-approved plans to share.
AB 1332 (Gov. Code §65852.27) required every local agency to have an ADU plan-preapproval program by January 1, 2025. Free partner plans and ADU Express can speed review, but neither replaces a site-specific Modesto permit. See our pre-approved ADU plans guide.
ADU fees in Modesto
Modesto publishes a Building Safety fee schedule. The schedule labeled effective July 1, 2026 to June 30, 2027 lists Accessory Dwelling Units and small dwellings up to 1,200 sq ft at $2,429 per permit (includes mechanical, plumbing, and electrical in that line item). That is a published building-safety permit amount for that size band — not a total project cost. Other lawful fees and construction can add to that amount; the impact-fee exemptions below still apply. Ask Building Safety for an estimate for your scope: Building Safety Fees.
Typical California ADU cost buckets also include:
- School district developer fees
- Utility connection or capacity charges — see ADU utility hookup costs
- Impact fees. Under current state law (Gov. Code §66311.5, renumbered by SB 543, Stats. 2025, ch. 520, effective January 1, 2026), a local agency, special district, or water corporation may not impose an impact fee on an ADU that has 750 square feet of interior livable space or less, or on a JADU that has 500 square feet of interior livable space or less. Larger ADUs must be charged proportionately relative to the primary dwelling. Connection/capacity charges are separate but have their own limits and conversion-unit exemptions in §66311.5(b), (d) and (e). Details: ADU impact fees. Future, not current: From January 1, 2027, SB 1117 (Stats. 2026, ch. 809) changes proportional impact fees on ADUs over 750 square feet to cover only interior livable space above 750 for up to two ADUs on a lot; properties with more than two have a separate rule.
How long does an ADU permit take?
Modesto’s ADU Express offers coordinated review at an appointment for qualifying complete plans. Same-day approval is possible, not guaranteed; ask what remains before permit issuance.
Under Gov. Code §66317, written completeness notice is due within 15 business days of receipt; missing it makes the application (including a resubmittal) deemed complete. For a completed application on a lot with an existing single-family or multifamily dwelling, the decision is due within 60 days, otherwise deemed approved. An applicant-requested delay tolls that period. With a concurrent new primary dwelling application, the agency may wait for the primary permit decision, but ADU review remains without discretion or a hearing. These are review clocks, not construction or move-in dates. For qualifying detached applications using a current-code-cycle preapproved or identical previously approved plan, §65852.27(b) provides a 30-day completed-application decision rule. See ADU permit timelines.
What does an ADU cost in Modesto?
Beyond the published building-safety fee line above, we do not have Modesto-specific construction cost data we can cite. Costs depend on size, site conditions, design, utilities, and who builds. See our California ADU cost breakdown and get written contractor quotes.
Frequently asked questions
What is Modesto’s ADU Express program?
A one-hour appointment for coordinated city review of complete, professionally prepared ADU/JADU plans. Qualifying ministerial projects may receive same-day approval; revisions may still be needed, and participation guarantees neither approval nor construction timing. Modesto posts appointment instructions on its official ADU page.
Can I build a JADU in Modesto?
A JADU is no more than 500 square feet of interior livable space, within the walls of a proposed or existing single-family residence; an attached garage counts, a detached accessory structure does not. It needs an efficiency kitchen and an entrance separate from the main entrance. Shared sanitation also requires interior entry to the main living area (Gov. Code §§66313(d), 66333(d)–(f)). Under Gov. Code §66333(b), owner-occupancy is required only if sanitation is shared: the owner may live in the main home or JADU. No owner-occupancy is required for separate sanitation, or when the owner is a governmental agency, land trust or housing organization. Confirm the required deed restriction with Planning.
Do I have to live on the property to build an ADU?
For a regular ADU, state law generally does not let cities require owner-occupancy. JADUs can differ when sanitation is shared. Ask Planning about recorded covenants on your lot.
Is SB 9 the same as an ADU?
No. SB 9 covers certain second primary dwellings and lot splits. See SB 9 vs ADU.
Can I sell my Modesto ADU separately from the house?
Usually not unless the city has opted into AB 1033 with a local ordinance. We did not find an official City of Modesto opt-in statement on the ADU page we checked, so ask Planning before you plan on a separate sale. See selling an ADU separately.
Is my parcel under county rules?
Only if it is outside Modesto city limits. Unincorporated parcels use Stanislaus County’s ADU process. City and county share some free plan sets, but permits are issued by the jurisdiction where the lot sits.
Official links
State-law and key local-source recheck: November 6, 2026. Posted amounts and programs can change; resolve the specific conflicts noted above before relying on them.
- City of Modesto — Accessory Dwelling Units
- City of Modesto — Building Safety Fees
- Planning: planning@modestogov.com · 209-577-5267
- Building Safety / ADU Express: Permits@modestogov.com · 209-577-5232
- Stanislaus County — Accessory Dwelling Units
- HCD ADU Handbook
- California HCD ADU page
For statewide and inland context, see our California ADU guide, California ADU laws for 2027, and Sacramento–Fresno inland ADU rules.
Browse the California housing education hub for related guides.
HomeBuyers Alliance is a nonprofit. We don’t sell ADUs, refer contractors, or take payment from builders. This page is general information, not legal advice. Rules change, so confirm everything with the City of Modesto before you design, buy, or build.
Primary sources
- City of Modesto — Accessory Dwelling Units — Modesto Municipal Code §10-4.115
- City of Modesto — Building Safety Fees — Schedule effective July 1, 2026–June 30, 2027
- Stanislaus County — Accessory Dwelling Units
- HCD Accessory Dwelling Unit Handbook — Gov. Code §66310 et seq.; §66311.5; §66317
- California HCD — Accessory Dwelling Units
- Gov. Code §66311.5 — ADU fees — Current text checked November 6, 2026
- Gov. Code §66317 — ADU review clocks — Current text checked November 6, 2026
- Gov. Code §66313 — ADU and JADU definitions — Current text checked November 6, 2026
- Gov. Code §66333 — JADU requirements — Current text checked November 6, 2026