In California, a newly built detached ADU is generally treated as a new home under the Title 24 Energy Code and usually needs solar. Attached ADUs and conversions of existing space don't.
In California, a newly built, detached ADU is treated as a new single-family building under the Title 24 Energy Code, so it generally needs solar panels. Attached ADUs and conversions of existing space are treated as additions and don’t. Some exceptions apply, such as too little usable roof area, and your building department applies the code.
This page covers California’s statewide Energy Code (Title 24, Part 6). Other states work differently, and your city or county may add local rules. Verify with your building department.
HomeBuyers Alliance is a 501(c)(3) nonprofit. We make no contractor or solar-company referrals and don’t sell plans. This guide is education only.
Solar is one of those ADU questions that surprises people late in design. The answer mostly depends on one thing: is your ADU a brand-new, freestanding building, or is it part of (or carved out of) something that already exists? For the bigger picture, see our California ADU guide.
Why ADUs touch Title 24
ADU zoning rules live in state ADU law (Gov. Code §66310 et seq.). Energy rules are separate. They come from the California Energy Code, part of Title 24, which the California Energy Commission (CEC) maintains.
The current cycle is the 2025 Energy Code. The CEC says buildings whose permit applications are applied for on or after January 1, 2026, must comply with it. Projects applied for earlier may fall under the 2022 code, so ask which cycle your permit uses.
The CEC’s 2025 ADU FAQ says an ADU counts as a “newly constructed building” if it’s a new, detached structure, and it must then meet the rules for a new single-family building. That includes solar PV under Section 150.1(c)14.
New detached vs. attached vs. conversion
This table summarizes CEC and HCD guidance for California. Your building department makes the call on your project.
| ADU type | Solar PV required under Title 24? | Source |
|---|---|---|
| New, detached ADU | Generally yes, unless an exception applies | CEC 2025 ADU FAQ; HCD Handbook |
| Attached ADU (addition to the home) | No, treated as an addition | CEC 2025 ADU FAQ |
| Conversion of existing space (garage, basement, room) | No, per HCD | HCD Handbook |
| Existing detached building converted to living space | No, per HCD | HCD Handbook |
HCD’s 2026 ADU Handbook says ADUs “constructed within existing space, or as an addition to existing homes, including detached additions where an existing detached building is converted from non-residential to residential space, are not subject to” the solar requirement. That’s good news for garage conversions. Manufactured homes are excluded from the requirement too.
Not sure whether your project is new, attached, or a conversion? The free ADU planner can help you sort it out.
Exceptions to the solar rule
The CEC’s 2025 single-family solar FAQ lists exceptions that can remove or shrink the requirement:
- Small usable roof. No PV is required if the solar access roof area (SARA) is less than 80 contiguous square feet. On steep-sloped roofs, areas facing between 300 and 90 degrees from true north don’t count.
- Tiny required system. No PV is required if the calculated minimum size is below 1.8 kWdc.
- Snow load. No PV is required if the building official finds the system can’t meet the specified snow-load standard.
- Older approvals. Some buildings approved by the local planning department before January 1, 2020, with mandatory conditions of approval.
- Battery storage. Pairing PV with a qualifying battery can reduce the required size by 25%.
Shading matters indirectly, because it affects which roof area counts. Your energy consultant or plan checker will run the numbers; don’t assume an exception applies until they confirm it.
Can the solar go on the main house?
Yes, with conditions. HCD says, citing the CEC, that the system can be installed on the ADU or on the primary home. The CEC’s 2025 FAQ adds that new PV modules can be added to an existing system, not necessarily on the ADU, if they’re part of the ADU’s permit application and sized to code.
What doesn’t work: counting panels you already have. The CEC says a new detached ADU needs newly installed PV; an existing system alone doesn’t satisfy the rule.
What will solar cost?
We don’t estimate a dollar amount here. System size depends on climate zone and the ADU’s conditioned floor area, and prices vary widely. Get the required size from your Title 24 report, then compare written quotes. Our ADU cost breakdown and utility hookup costs pages cover the rest of the budget. For recent law changes, see California ADU laws.
Frequently asked questions
Does a garage conversion ADU need solar in California?
Generally no. HCD says ADUs built within existing space, including converted detached buildings, aren’t subject to the Energy Code solar requirement.
Does an attached ADU need solar?
No. The CEC treats attached ADUs as additions, and solar PV isn’t required for additions.
Can I use my home’s existing solar panels for the ADU?
Not by themselves. The CEC says a new detached ADU needs newly installed PV, though the new modules can be added to the main house’s system.
Which Title 24 cycle applies to my ADU?
The CEC says permit applications filed on or after January 1, 2026, follow the 2025 Energy Code. Confirm with your building department.
Who can answer a specific Title 24 question?
The CEC runs an Energy Standards Hotline at 800-772-3300 and takes email at title24@energy.ca.gov, per HCD’s Handbook.
Rules vary by project, so verify with your city or county building department. When you’re ready to map out your whole project, the free ADU planner is a good next step.
Primary sources
- California Energy Commission — 2025 Energy Code Accessory Dwelling Units (ADU) FAQs
- California Energy Commission — 2025 Single-Family Solar PV FAQs
- California Energy Commission — 2025 Building Energy Efficiency Standards
- HCD Accessory Dwelling Unit Handbook (March 2026) — Solar Requirements section; Gov. Code §66310 et seq.
- California HCD — Accessory Dwelling Units